Project 3.11:Assessment of Micropile-Supported Integral Abutment Bridges

Assessment of Micropile-Supported Integral Abutment Bridges PHASE 2: Flexural Strength and Durability of Micropile Threaded Connections

Project 3.11

Project Summary

Integral abutment bridges (IABs) are the preferred method of construction by Maine Department of Transportation (DOT) and other transportation agencies throughout the United States due to their durability and reduced upfront and life-cycle costs. Shallow bedrock, commonplace at bridge sites throughout the state of Maine, has precluded the use of conventional driven pile foundations and IABs in some instances. Micropiles are an attractive foundation alternative at shallow bedrock sites where conventional foundation systems (e.g. driven piles) cannot develop sufficient length to achieve fixity and/or adequate geotechnical resistance. These foundation elements can be installed through challenging glacial geology, including boulder material and bedrock. Currently, there is no guidance on the design of micropile-supported IABs, or long-term instrumentation data capturing their performance. The objective of this study is to develop a design methodology and engineering recommendations for the structural and geotechnical design of micropiles for IABs, and to demonstrate that micropiles satisfy strength and stability requirements for IAB applications when shallow bedrock is present.

Principal Investigator

Dr. Aaron Gallant

Co-PIs

Dr. Bill Davids

Institution:

University of Maine

Project Status

Active

Project Cost

$398,792

Start Date

09/01/2019

Project Type

Base-funded

End Date

09/30/2024

Agency ID

69A3551847101

Sponsors:

Office of the Assistant Secretary for Research and Technology, University Transportation Centers Program, Department of Transportation, University of Maine, MaineDOT

Implementation of Research Outcomes:

This project is in its initial research phase. Implementation of research outcomes will be reported upon completion of the research outputs.

Impacts and Benefits of Implementation:

This project is in its research phase. Impacts and benefits of the research will be reported after the implementation phase.

Printable Project Information Sheet

December 2019 Quarterly Progress Report

March 2020 Quarterly Progress Report

June 2020 Quarterly Progress Report

September 2020 Quarterly Progress Report

December 2020 Quarterly Progress Report

March 2021 Quarterly Progress Report

June 2021 Quarterly Progress Report

September 2021 Quarterly Progress Report

December 2021 Quarterly Progress Report

March 2022 Quarterly Progress Report

June 2022 Quarterly Progress Report

September 2022 Quarterly Progress Report

December 2022 Quarterly Progress Report

March 2023 Quarterly Progress Report

June 2023 Quarterly Progress Report